Development and Capacity Expansion Project of Sofian Cement Plants

سیمان صوفیان
Part One

Supply and fabrication of 2,000 tons of mechanical equipment for lines 3 and 4 of the development and capacity expansion project of Sofian Cement Plants, including preheater and rotary kiln, grate cooler, raw mills, crushers, stacker and reclaimer, metal structures, and more.

  • Client: Sofian Cement Company
  • Contractor: Arman Sanat Tadbir Andish Company
  • Consultant: HOLTEC Company
  • Supervising Authority: Fars and Azarbaijan Cement Engineering Services Company (FA)
  • Project Location: Sofian, East Azerbaijan
  • Progress Percentage: 100%
  • Execution Time: Year 2005
  • Project Status: Completed
  • Execution Duration: 48 months (including two execution units: Unit 3 and Unit 4)
  • Quality Control Tests: VT – DT – MT – PT – RT – UT
سیمان صوفیان
سیمان صوفیان
سیمان صوفیان
سیمان صوفیان
Part 2

Cold and hot installation and commissioning of 13,000 tons of mechanical equipment for lines 3 and 4 of the development and capacity expansion project of Sofian Cement Plants, including preheater and rotary kiln, grate cooler, raw mills, crushers, stacker and reclaimer, metal structures, and more.

  • Client: Sofian Cement Plants
  • Contractor: Arman Sanat Tadbir Andish Company
  • Project Location: Factory site in Sofian County
  • Project Operation Location: Factory site in Sofian County
  • Execution Time: Year 2006
  • Project Quality Control Tests: VT (Visual Testing) – PT (Penetrant Testing) – UT (Ultrasonic Testing) and dimensional inspection
سیمان صوفیان