Installation and Commissioning of Electrical and Instrumentation Systems for Gasoline Unit at Tabriz Refinery

Execution of electrical and instrumentation equipment installation operations for the gasoline production unit at Tabriz refinery

  • Employer: Tabriz Refinery (Tanavob Company)
  • Contractor: Arman Sanat Tadbir Andish Company
  • Consultant: Tanavob Company
  • Status: Ongoing
  • Execution Time: 2013
  • Progress: 100%
  • Process Units: Catalyst, Octane, Hydrogenation, Extraction
  • Utility Units: Water, Air, Nitrogen, Wastewater