Mechanical Equipment and Piping of Masjed Soleyman Dam and Power Plant Projects Installation and commissioning of mechanical equipment and piping for Masjed Soleyman power plant expansion project Employer: Farab CompanyContractor: Arman Sanat Tadbir Andish CompanyConsultant: Farab CompanyProject Operation Location: Khuzestan Province – Masjed Soleyman Power PlantProject Location: Arman Sanat Tadbir Andish Company Site – Masjed Soleyman – Masjed Soleyman Power PlantStatus: CompletedProgress: 100%Execution Time: 2003Project Quality Control Tests: RT, PT, MT, Hydro Test Worked Systems: Main Cooling System of the Power PlantAS System and AB System of the Power PlantAll Instrumentation Systems of the Power Plant Expansion ProjectDewatering System and Firefighting System of the Power Plant Project-related photos
Material Handling Equipment for the Wharf of the Persian Gulf Special Economic Zone of Metal and Mining Industries as EPC
Installation and Commissioning of Electrical and Instrumentation Equipment at Mahabad Petrochemical Complex